(1) For simple lighting and public power distribution, high-voltage metering is not required in the high-voltage wiring scheme of the prefabricated substation; only low-voltage metering or no metering is needed, and compensation is unnecessary. There are 4-6 outgoing circuits, controlled and protected by plastic circuit breakers.
(2) For power and lighting public power distribution, the number of outgoing circuits in the prefabricated substation increases to 8-12. In addition, reactive power compensation should be provided.
(3) Self-maintained power supply and special circumstances.
Prefabricated substations have a small footprint. Generally, a prefabricated substation occupies only 5-6 square meters, and can even be reduced by 3-3.5 square meters. Suitable for densely loaded industrial and mining enterprises, ports, and residential areas, it extends high-voltage power supply to the load center, reduces the low-voltage power supply radius, and lowers losses. Fewer low-voltage power lines are required, generally 4-6. This shortens the on-site construction period and reduces investment.